City Standards - Connecting Individual Buildings
Residential/Commercial Water Service up to 2 inches
The following steps will help you through the New Water Service Procedure:
STEP 1 Complete a Tap-In Permit Application, available at the Zoning Department, 46 North Ave, lower level or download here.
STEP 2 Schedule a Site Visit. It is crucial to identify where the water utility is located and in decide the best placement for your water tap and meter pit location before any excavation is done. The meter pit/shut off must be installed close to the city’s right-of-way and is not allowed to be installed within the driveway. At least a 48-hour notice is necessary to schedule a site visit. During the site visit, the completed application must be signed for approval by the Water Department. This must be done before the permit can be issued. To schedule your site visit, call 330-633-0851.
STEP 3 Submit the application and necessary fees. Once the site visit is completed and the location for water service is determined, you will need to submit the approved Tap-In Permit Application and pay the necessary fees at the Zoning Department. The cost of the permit is a minimum $1,800 plus additional costs (Right-of-Way Bond and/or inspection fees), if necessary.
In the event a Right-of-Way Bond is required, the Contractor will be required to register with the City prior to issuance of the permit. The bond will be returned once all required inspections are completed by the Water Department.
STEP 4 Install the waterline. The waterline from the house to the right-of-way must be installed before the service connection is made by the Water Department. If your waterline is already in the ground, you must locate the water line before contacting the Water Department.
STEP 5 Contact the Water Department to connect service. Service connection will take place approximately 4-6 weeks after application, depending upon the workload of the Water Department and the weather. Once the service has been connected, the homeowner or contractor must contact the Water Department to have the meter installed at the street and the water service turned on.
STEP 6 Sign the contract within 2 weeks. Billing commences once the water is turned on. A contract must be signed within two weeks after the service is turned on to avoid disconnection.
Please contact the Water Department at 330-633-0851, Monday-Friday, 6:30 am to 3:00 pm with any questions.
Please note that as the property owner, you are responsible for the installation of the water line that runs from the house to the street/main shut off. The following standards must be followed:
- Water line must be 1 inch or larger and 5 feet deep
- Pipe used must be Type K copper tubing
- Line must be straight from the house to the ditch or curb line, curled up to grade level
- Water line must have an initial 18 inches of backfill consisting of either fill sand or dirt free of rocks and debris
- All waterlines must be inspected by the Water Dept. before backfilling, especially those with unions, joints, and other fittings
- Once the inspection is made, the service connection will be made by the Water Dept.
- All water service material needed to connect from the main to the house line will be supplied by the Water Dept including the tapping saddle, corporation, type K copper pipe, meter setting, meter, meter pit, casting and lid. If meter is installed inside, a curb stop valve and box will be provided instead of meter pit supplies
- The water line and sanitary sewer line must be installed in separate ditches with a minimum of 10 feet horizontal separation and have an 18-inch vertical clearance when crossing
- The water service shall not be installed directly across from or underneath the driveway approach
- The homeowner is responsible for landscape repairs around the new meter pit on their side of the street. The city will make repairs to the opposite side of the street due to the location of the main waterline tap if necessary.
- Service line must be insulated as it enters the basement through the wall or floor and extend not less than 4 inches before being fitted with a stop and waste cock (shut-off valve) – not to exceed 12 inches where the line enters the basement
- House numbers must visible and easily identifiable in plastic, metallic, or painted numerals before meter is installed
- Any jumpers found in place of the meter will be removed and water shut off at the curb. Water will not be turned on until a fee of $250.00 has been paid.